Wednesday, October 17, 2012

Planning Construction!

Hello all!

The YR&G Board has approved the project and we are starting to make plans for construction. The basic thought is to construct the pavilion over several weekends next June (2013).

June 1-7 Week - Material Staging
  • Materials get delivered during the week
June 8-9 Weekend - Foundation
  • Dig Holes
  • Install Sonitubes
  • Mix and Pour Concrete
  • Install Strong Ties
  • Move rest of the building supplies to the range
June 15-16 Weekend - Main Construction
  • Posts
  • Beams
  • Roof
  • Front Overhang
  • Shooting bench and seat
  • Picnic Table
June 22-23 Weekend - Alternate (in case of earlier weekend rain)